Line 9: | Line 9: | ||
** Linux static 32b | ** Linux static 32b | ||
** Sugar | ** Sugar | ||
* Progress on new Makefile | * <s>Progress on new Makefile</s> | ||
''No kiwix release as beta6 is not ready.'' | |||
== Week 13 == | == Week 13 == | ||
* <s>aria2 for OSX</s> | |||
** Universal binary | |||
** Complete package | |||
** Integrate upstream | |||
* Makefile ready | * Makefile ready | ||
** Linux static 32b | ** Linux static 32b |
Revision as of 14:41, 12 March 2012
B&W activities/development planning.
Week 11 (this week)
Sugar bug fix (toolbar/UI size)
Week 12
- Kiwix release
- compilation on OSX
- Linux static 32b
- Sugar
Progress on new Makefile
No kiwix release as beta6 is not ready.
Week 13
aria2 for OSX- Universal binary
- Complete package
- Integrate upstream
- Makefile ready
- Linux static 32b
- Linux static 64b
- Linux shared 32b
- Linux shared 64b
Week 14
- Makefile with OSX
- OSX 32b (static)
- OSX 64b (static)
Week 15
- Debian package
- rewrite debian package rules
- integrate/write man pages
- resubmit request to vasudev
- (split up into 2 packages with kiwix-serve and kiwix)
Week 16 (start of April)
- Document Windows setup
Week 17
- Makefile with Windows
- Windows 32b
- Windows 64b
Week 18 & 19
- Compilation farm software + setup
Week 20
- Compilation farm.