B&W activities/development planning.
Week 11
Sugar bug fix (toolbar/UI size)
Week 12
- Kiwix release
- compilation on OSX
- Linux static 32b
- Sugar
Progress on new Makefile
No kiwix release as beta6 is not ready.
Week 13
aria2 for OSXUniversal binaryComplete packageIntegrate upstream
- Makefile ready
- Linux static 32b
- Linux static 64b
Linux shared 32bLinux shared 64b
Week 14
- Makefile with OSX
- OSX 32b (static)
- OSX 64b (static)
Week 15
- Debian package
- rewrite debian package rules
- integrate/write man pages
- resubmit request to vasudev
- (split up into 2 packages with kiwix-serve and kiwix)
Week 16 (start of April)
- Document Windows setup
Week 17
- Makefile with Windows
- Windows 32b
- Windows 64b
Week 18 & 19
- Compilation farm software + setup
Week 20
- Compilation farm.